master

Construct New Science Building


Friday, April 12, 2019
Complete

Science Hall Exterior

Upon arrival at the campus, the first thing one will see is the new Science Building, due to its location at the corner of Plattekill Avenue and South Manheim Boulevard. It will enhance student-faculty interactions and provide improved interdisciplinary teaching laboratories and classrooms. Academic departments that will have offices in the new building include computer science; geology; mathematics; physics and astronomy; and geography.


The ribbon cutting ceremony was held on March 9, 2017. The academic departments have moved in, faculty and staff have set up their new homes, and the students are enjoying the new facilities.


Estimated Cost$48,026,000
Estimated Date of CompletionJanuary 2017
ArchitectZimmer Gunsul Frasca Architects
Construction ManagerSUCF
College RepresentativeJeff Lewis, Campus Architect/Garry Nack, Project Manager
ContractorNiram (Boonton, N.J.)
Square Footage
CategoryAcademic & Administrative Projects (SUCF), Facilities Master Plan
Source of FundingCapital