College Hall Transformer


Tuesday, March 26, 2019
Complete

Replace a 500Kva transformer that malfunctioned in 1994 and was replaced by a temporary 225Kva transformer.  The new 500Kva transformer will be installed in the existing cabinet and meet the full electrical load requirements of College Hall.


A 500Kva Olsum transformer has been installed and is fully
operational.

Project is complete.


Estimated Cost$35,000
Estimated Date of CompletionDecember 15, 2005
ArchitectFacilities Management Replacement
Construction Manager
College RepresentativeDale Coon, Facilities/Project Manager
ContractorTo be determined
Square Footage
CategoryAcademic & Administrative Projects (SUCF)
Source of FundingCapital