Elting Gymnasium Multi Purpose Room 101 Renovation
Tuesday, March 26, 2019
Complete
Renovation of room 101 to include removal of existing asbestos flooring and specified wall pads, windows, floor and ceiling tiles and lighting fixtures. Provide new flooring, mirrors, windows, ceiling tiles and lighting fixtures for the space.
The new room is complete and looks great.
Estimated Cost | $125,000 |
Estimated Date of Completion | August 2008 |
Architect | Michael Weatherly, Architectural Designer |
Construction Manager | |
College Representative | |
Contractor | LKM Elec.;Transitional Builders; MSE; John Herbert |
Square Footage | 1545 SF |
Category | Locally Managed Projects |
Source of Funding |