Install a fully addressable fire alarm system in the Fine Arts Building.
The fire alarm installation is complete.
Estimated Cost | $198,975 |
Estimated Date of Completion | January 2008 |
Architect | HA2F Engineering |
Construction Manager | Lyle Nolan- Project Manager |
College Representative | |
Contractor | Hudson Valley Electrical Construction & Maintenance |
Square Footage | |
Category | Locally Managed Projects |
Source of Funding | Capital |