Humanities, Jacobson Faculty Tower, Lecture Center & Sojourner Truth Library
Tuesday, March 26, 2019
Complete
Provide air conditioning throughout Humanities as well as new chiller(s) for Humanities, Jacobson Faculty Tower and Lecture Center.
This project has been completed and cool air has been flowing throughout the buildings.
Estimated Cost | $8,500,000 |
Estimated Date of Completion | Summer 2008 |
Architect | PB Powers Engineering/ NYPA |
Construction Manager | NYPA with Garry Nack as Campus Liason |
College Representative | John McEnrue, Director Facilities Design & Construction |
Contractor | New York Power Authority/Dynamic Mechanical |
Square Footage | |
Category | Locally Managed Projects |