Residence Hall Fire Alarm Upgrade, Phase III
Tuesday, March 26, 2019
Complete
The Residence Hall Fire Alarm Upgrade project was awarded to J.J.Sass Electric Corp. in the spring of 2003. In order to keep 11 dormitories occupied and Hasbrouck Dining Hall in service during the academic year, the fire alarm project was phased over three summer breaks: May 25th - August 15th of 2003, 2004 and 2005.
Project complete.
Estimated Cost | $2,356,000 (all phases) |
Estimated Date of Completion | Spring 2006 |
Architect | HA2F Engineering |
Construction Manager | Dale Coon, Facilities/Project Manager |
College Representative | Dale Coon |
Contractor | J.J.Sass Electric |
Square Footage | |
Category | Academic & Administrative Projects (SUCF) |
Source of Funding |