Scudder Hall Student Room Renovations


Tuesday, March 26, 2019
Complete

The College is starting the last phase of flooring and pipe insulation abatement in the older residence halls. Vinyl asbestos floor tile, and pipe insulation and fittings in Scudder Hall student rooms and maintenance/service areas will be removed.

Insulation and flooring will be replaced with new materials, and the walls and ceilings will get a fresh coat of paint.


The project is complete. The student rooms in Scudder Hall have new paint and new flooring.


Estimated Cost$460,000
Estimated Date of CompletionAugust 2010
ArchitectMegan Smailer, Campus Architect
Construction ManagerFrank Wood, Construction Manager
College Representative
ContractorPerfezione Painting, Continental Flooring, Adelaide Abatement
Square Footage
CategoryLocally Managed Projects
Source of Funding