Service Building Renovation
Facilities Operations & Maintenance, Environmental Health & Safety, Facilities Design & Construction, and the University Police Department are in need of updated facilities. The defunct kitchen facilities' old meat and vegetable coolers have been used to provide temporary storage, and those spaces are not at capacity and not easily accessible. Growing needs of the departments require additional office space and storage/filing space. University Police is compromised, as it is housed in a space that is inadequate for day-to-day departmental operations. The custodial department that has been housed in the basement of College Hall and the new Office of Campus Sustainability will be housed with the rest of Facilities Management to better meet the needs of the department as a whole.
The work on both phases of this renovation is complete. Facilities Design & Construction, University Police and Environmental Health & Safety are located upstairs in the newly renovated space. Facilities Operations & Maintenance, including the Custodial department, have moved into the newly renovated space on the lower level.
Estimated Cost | $5,000,000 |
Estimated Date of Completion | Spring 2016 |
Architect | Architecture + |
Construction Manager | Garry Nack, Project Manager |
College Representative | Michael Weatherly, Architectural Designer |
Contractor | MLB (Malta, N.Y.) |
Square Footage | 38,000-sf building. Renovated area 20,000 sf. |
Category | Locally Managed Projects |
Source of Funding | Capital |