van den Berg Hall Roof Renovation


Tuesday, March 26, 2019
Complete

The roof at van den Berg Hall needs to be restored to maintain the useful life of the roof, in addition to addressing the current snow guards that will be replaced to adequately hold properly.


The new roof is complete and the new snow guards are in place.


Estimated Cost$785,000
Estimated Date of Completionsummer 2017
ArchitectArchitectural Preservation Studio DPC, NY, NY
Construction Manager
College RepresentativeKemp Anderson- Project Manager
ContractorSandhu Contracting Inc, Astoria, NY
Square Footage
CategoryAcademic & Administrative Projects (SUCF), Locally Managed Projects
Source of FundingCapital